January 28, 2025 Project Update to City Council

On January 28, 2025 City Staff presented the Vallejo City Council with an update on the Broadway Project.

At the meeting staff presented the January 13, 2025 construction schedule. Some major highlights from the schedule are:

  • 3/28/25 - Temporary Certificate of Occupancy
  • 4/25/25 - Final Certificate of Occupancy (construction completion)
  • 6/28/25 - Full occupancy of residents

Please note that this schedule does not make assumptions or hold contingency for potential inclement weather delays and was based on best case scenario with no outside contributing factors.

The balance of funding remaining to finish the project is $4.5M and is anticipated to be sufficient to complete the project on schedule.

Visit the link to see the full presentation and supporting documents: https://vallejoca.portal.civicclerk.com/event/3110/media

Staff will be providing monthly updates on project status and budget at Council Meetings through project completion.